Update on PJM Cost Allocation Dispute: FERC’s March 2026 Remand Order and the Path Ahead for Short-Circuit Projects
By: Ric Austria, Executive Principal, Pterra Consulting and Cherry Bautista, Principal Engineer, Pterra Consulting
In May 2025, we highlighted a proposed settlement in the
long-running PJM Interconnection cost allocation dispute as a potential step
toward fairness and grid reliability. That agreement, advanced by the Indicated
PJM Transmission Owners (ITOs), Long Island Power Authority (LIPA), Neptune
Regional Transmission System, LLC, and supported by Pterra’s technical
analysis, aimed to address key flaws in PJM’s solution-based Distribution
Factor (DFAX) methodology through targeted revisions to Tariff Schedule 12.
On March 6, 2026, the Federal Energy Regulatory Commission
(FERC) issued its Order on Remand (194 FERC ¶ 61,179) in the consolidated
proceedings (Docket Nos. EL15-18 et al., EL21-39-000, ER22-1606-000, and
related cases). This order significantly advances the issues while leaving one
critical question open for further development.
Key Outcomes from the March 2026 Order
FERC’s ruling resolves several core disputes in favor of the
complaining parties (including Consolidated Edison, Linden VFT/GE successors,
Neptune/LIPA, and others):
- Elimination
of the 1% De Minimis Threshold Exemption
FERC found the de minimis provision unjust, unreasonable, and unduly discriminatory under the Federal Power Act. It violates the cost causation principle by exempting larger zones from cost responsibility simply due to their size relative to peak load, while smaller zones or merchant transmission facilities bore disproportionate shares.
FERC directed PJM (on behalf of the Transmission Owners) to file tariff revisions eliminating the exemption, effective retroactively to June 18, 2015 (the date of initial Commission error in denying the Con Edison complaint). PJM must recalculate cost responsibility assignments for all affected RTEP projects back to that date and issue refunds/surcharges with interest within 90 days. The potential cost impact is estimated at $100 million or more for the 2020-2022 period alone. - Rejection
of the Host Zone Proposal and Related Settlement Elements
The order rejected the ITOs’ Host Zone Proposal (ER22-1606-000) and associated settlement filings, which retained modified forms of the de minimis exemption. These were deemed inconsistent with the D.C. Circuit’s 2022 remand opinion. - Netting
Practice Upheld
Challenges to PJM’s netting of positive and negative flows within a zone under DFAX were denied. FERC affirmed prior findings (upheld by the D.C. Circuit) that netting reasonably accounts for counterflows that create additional transmission capacity, consistent with zonal cost allocation principles. - Reallocation
Following Con Edison TSA Termination
FERC affirmed the 2017 Cost Reallocation Order (ER17-950-006), confirming PJM’s use of the then-effective Schedule 12 methodology after termination of Con Edison’s transmission service agreements.
The Remaining Open Issue: Short-Circuit Reliability
Projects
The order establishes paper hearing procedures to develop
additional record evidence on the application of the solution-based DFAX method
to transmission facilities addressing short-circuit reliability violations
(e.g., overdutied breakers due to excessive fault current).
FERC questions whether DFAX based on steady-state power
flows are just and reasonable for these projects, given that short-circuit
issues are not flow-driven like thermal constraints. The Commission draws
parallels to its prior rejection of DFAX for stability violations (replaced by
the Stability Deviation Method in the Artificial Island proceedings) and seeks
input on:
- Whether
short-circuit projects differ sufficiently from stability or flow-based
needs to justify continued use of DFAX.
- If
DFAX fails cost causation here, what replacement methodology would
allocate costs roughly commensurate with benefits (e.g., proportional
contribution to fault current, similar to concepts in Order No. 2023 for
generator interconnection short-circuit upgrades).
Initial comments are due approximately 90 days from issuance
(early June 2026), with replies 60 days later.
Implications and Next Steps
The March 2026 order marks substantial progress toward
equitable cost sharing in PJM, particularly by removing the de minimis
exemption and triggering long-overdue billing corrections. However, the
short-circuit question remains pivotal, as many RTEP projects (including
Bergen-Linden Corridor and Sewaren) were driven primarily by fault-duty
concerns.
Pterra’s prior work, including detailed affidavits submitted
in the original Con Edison complaint (Docket No. EL15-18-000) analyzing the
flawed application of DFAX to the Bergen-Linden Corridor and Sewaren projects
and the 2021 affidavit in the Neptune/LIPA proceeding (EL21-39-000)
demonstrating an alternative nodal DFAX approach that eliminated netting and
the de minimis threshold, contributed meaningfully to this process. Through
rigorous engineering analysis, clear quantification of disproportionate allocations,
and objective comparisons of methodologies, Pterra’s contributions helped
illuminate the practical shortcomings of the existing DFAX framework in meeting
cost causation principles. This body of work provided FERC with concrete,
data-driven insight into how the de minimis exemption produced irrational and
discriminatory outcomes. Ultimately, these efforts provided guidance to the
Commission in its decision to eliminate the de minimis threshold, direct
retroactive recalculations and refunds, and open the current paper hearing to
explore more appropriate cost allocation approaches for short-circuit
reliability needs.
