|

Why Not Voltage Uprating as a Planning Option?
July 2005
By R. Austria, Pterra Consulting
Voltage uprating is a technology that is actually a
combination of techniques known for many years by folks in the line
design area, for instance from the
Towers, Poles and
Conductors (TP&C) Line Design Subcommittee of the
IEEE. It is a possible planning alternative to techniques which aim to
increase the current capacity of transmission lines, known collectively
as current uprating. Both voltage and current uprating share the
common objective of utilizing the existing right-of-way and structures
to transfer more power.
From a planning perspective, voltage uprating is an option
that works alongside such others as converting AC lines to DC (including
the new "tripole" concept), and increasing phase order, which makes it a
candidate for planners looking to make the most out of existing
infrastructure. So, the $64 dollar question is: "Why isn't it
planned for more often?"
In one view, the lack of application may come from the lack of
planning confidence that the technology is viable for
specific projects. More than current uprating, or for that matter,
AC-to-DC conversion, the feasibility and cost of voltage uprating is
dependent on a detailed assessment of the existing line. There
are precious few actual examples, some of which include: Fairmount-Port
Angeles and Bell-Boundary, both in BPA, 115 to 230 kV; multiple lines in
Public Service of Colorado (PSCo), 115 to 230 kV; and Jamestown-Grand
Forks in North Dakota, 115 to 230 kV. In the example of PSCo,
there is clearly an advantage in a collective company experience of
uprating several lines. The cost experience appears to indicate
that a 115 to 230 kV uprate would come in at about 70% the cost of a
complete rebuild; a good planning figure, but actual costs can vary
significantly.
In recent work by Pterra Consulting, we had an opportunity to
include voltage uprating amongst the planning options. The work
involved planning for long-term development of an urban, congested
area, where new right-of-way was difficult, if not, impossible to
obtain. The load growth required doubling capacity on
several 115 kV lines. Uprating to 230 kV allowed the uprated
circuits to connect to the existing 230 kV system, saving on the cost of
new transformers. With a 30% cost savings over re-building the
lines, voltage uprating proved to be a cost-effective option that
became an integral component for the overall plan.
But one sample doesn't make a statistic, and it would probably take a few more case studies and practical
experience to get voltage uprating into the planning mainstream.
The link between planner and line designer needs to be strong in
order for voltage uprating to be a viable planning option. As
stated in a
TP&C panel session held at the
2005 General Meeting, Power Engineering Society, 12-16 June 2005, in San
Francisco, California USA:
- for short-term planning, quick turnaround on feasibility
assessments for voltage uprating are important,
- and for long-term planning, the voltage uprate must be part of a
robust solution (fits multiple future scenarios), cost less than a
line rebuild, and cost about the same or less than the per capacity MW
addition of current uprating techniques.
For the full pdf of the panel session, click
here.
For questions, comments and further discussion, contact me at
ricaustria@pterra.us.
© 2005. All rights reserved.
|